Wednesday, June 15, 2011

K-7 and Johnson Drive Interchange Project Update-June 2011

Attention, Western Shawnee residents!  Weather permitting, on Thursday/Friday, June 16-17, new traffic changes are scheduled to take place on the K-7 and 55th Street/Johnson Drive interchange project in Johnson County.  The traffic changes that are scheduled to occur are as follows:
·         On Thursday, June 16, after morning rush hour (weather permitting), access from northbound and southbound K-7 to Clear Creek Parkway on the west side of K-7 will be closed to all traffic.  Utility work as well as construction work will begin on the new bridge that will span over K-7 at Clear Creek Parkway.
·         On Friday, June 17, before morning rush hour (weather permitting), 55th Street will be reopened to traffic for all through eastbound and westbound movements from 55th Street to Johnson Drive.  Also, access from northbound K-7 to westbound 55th Street and from 55th Street/Johnson Driver to southbound K-7 will be opened to all traffic at the same time.  If there is any wet weather that occurs on Thursday, June 16, the 55th Street traffic changes will shift to sometime during the day on Friday, June 17, and will not be in place before morning rush hour. 

Stay tuned for more information as the construction progresses.

Tuesday, March 1, 2011

K-7 and Johnson Drive Interchange Project Update-March 2011

If Mother Nature decides to play nice over the next week or so, new traffic changes will be set to take place on the K-7 and Johnson Drive interchange project in Johnson County the week of March 7th or March 14th.

What do you have to look forward to?  First of all, northbound and southbound K-7 will be reduced to one lane...moving you over to the new northbound lane so that crews can complete construction on the new southbound lanes.  This will last through late fall, weather permitting.

Second, and this is a biggie, the east leg of Clear Ceek Parkway will be closed for bridge constuction that will take Clear Creek traffic over K-7.  In other words, no more direct access to K-7 from Clear Creek.  Detours will take you to either Shawnee Mission Parkway or 47th Street, depending on where your destination is.

Lastly, access from southbound K-7 to 55th Street will be closed through Aprill 2011 (again, depending on the weather) while crews complete construction on the new southbound lanes.

I'll keep you posted on any other traffic updates for this ever changing area.  If you have any questions, please feel free to email or give me a call!


Wednesday, July 7, 2010

K-7 and Johnson Drive Interchange Project Update

Even though construction began just a few months ago, you can already see the progress crews have made on the new K-7 bridges that will cross over Johnson Drive.  However, beginning on Monday, July 12th (subject to change though), access to Johnson Drive/55th Street just west of Hedge Lane Terrace from northbound and southbound K-7 will be closed to ALL traffic so that crews will be able to begin work on the roundabout that will be located east of Meadowview Drive.  The traffic lights will still be operational during this phase and people should still be able to access the Crouch Corners and Oak Valley West Shopping Centers from north and southbound K-7.  Here's what the projected roundabout is to look like:


Once this project is completed, which is tentatively scheduled for the Fall of 2011, it should greatly improve traffic levels for this rapidly growing area of Western Shawnee.